Construction Update

August 2019

Construction is going very well and we are nearing completion on building 1000.
Here is the most recent news on the building construction.

 

Building 1000

We are in the final stages of completing this building! The siding, stucco and stone is being worked on and will be finished by the end of the month. The elevator is being installed and suites will be close to completion by the end of September.

 

Building 2000

The framing of building 2000 is 100% complete. We will be working on the siding and stucco through September. The cabinets and the elevator are being installed  this month.

  

Buildings 3000

The framing of building 3000 will be completed by the end of the month. Siding & Stucco began being installed August 1. Drywall installation starts mid August.  The elevator will be delivered by the end of the month.

Buildings 4000

The framing of building 4000 will be completed by the end of the month. Drywall, siding and stucco to begin mid September and the elevator will be delivered by the end of September.

Site Work

Interior courtyard waterproofing started last month. Paving will be complete by mid September. Foundation is 100% complete. The rough-ins in the parkade are ongoing.

April 2019

What a winter we had! Our builders worked through the cold months with ample amounts of hot chocolate and determination. Here is the most recent news on the building construction.

 

Building 1000

The framing of Building 1000 is 100% complete and windows are currently being installed on the west side of the building. Plumbing pipes, duct work and electrical conduit are being sourced and being brought in for installation. The building envelope (the physical separator between the outside and inside environment of the building) is beginning to be built.

 

Building 2000

The framing of building 2000 is 90% complete and we are starting to work on the firewall and framing of the east side of the building.

  

Buildings 3000 and 4000

The foundation is over half built and the plumbing pipes, duct work and electrical conduit are being sourced and being brought in for installation for the west half of the parkade.

January 2019 Update:

Construction is well underway and we are making great progress!​ 

  • The framing of building 1000 has started and building 2000 will commence before the end of February.

  • Footings, walls & columns under building 3000 are over 50% complete!

  • First S.O.G. pour under building 3000 scheduled to be completed by the end the month!

  • The Bulk excavation under Building 4000 is ongoing.

October 2018 Update:

  • All footings, columns, and walls have been completed in the West half of the Parkade.

  • 25% of slab on grade, on the west half of the foundation, is complete.
     

We are currently working on shoring for suspended slabs underneath Building 1000 and expect framing to start for that building on 1 December 2018. We are finishing up with permanent power infrastructure and transformer installation with Enmax to get permanent power to the site and will be closing 128 Avenue this coming weekend to tie in deep services.